top

  Info

  • Utilizzare la checkbox di selezione a fianco di ciascun documento per attivare le funzionalità di stampa, invio email, download nei formati disponibili del (i) record.

  Info

  • Utilizzare questo link per rimuovere la selezione effettuata.
Building contract claims [[electronic resource]]
Building contract claims [[electronic resource]]
Autore Chappell David
Edizione [4th ed. /]
Pubbl/distr/stampa Oxford, : Blackwell, 2005
Descrizione fisica 1 online resource (xi, 552 p. ) : ill
Disciplina 343.41078624
Altri autori (Persone) Powell-SmithVincent
SimsJohn <1929->
ChappellDavid
Soggetto topico Construction contracts - Great Britain
Breach of contract - Great Britain
Actions and defenses - Great Britain
Damages - Great Britain
Law
Construction contracts - England
Breach of contract - England
Actions and defenses - England
Damages - England
Law - Great Britain
Law - Non-U.S
Law, Politics & Government
Soggetto genere / forma Electronic books.
ISBN 1-280-21296-9
9786610212965
0-470-79917-X
0-470-75932-1
1-4051-4808-X
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto PART 1.1 Introduction.1.1 Structure of the book.1.2 Definitions.1.3 The basis of claims.1.4 Architect's and Contract Administrator's powers and liability to the contractor.1.5 Quantity surveyor's powers.2 Time.2.1 Time of the essence.2.2 Time at large.2.3 Extension of time clauses in contracts.2.4 Concurrency.2.5 Acceleration.2.6 Sectional completion.2.7 The SCL extension of time protocol.3 Liquidated damages.3.1 The meaning and purpose of liquidated damages.3.2 Liquidated damages or penalty.3.3 Liquidated damages as limitation of liability.3.4 Sums greater than a genuine pre-estimate.3.5 Liquidated damages as an exhaustive remedy.3.6 Injunction.3.7 Liquidated damages in relation to loss.3.8 Where there is no breach of contract.3.9 Calculation of liquidated damages.3.10 Maximum recovery if sum is a penalty.3.11 Maximum recovery if liquidated damages do not apply.3.12 Bonus clauses.4 Basis for common law claims.4.1 General.4.2 Implied terms in building contracts.4.3 Variation of contract.4.4 Omission of work to give it to others.4.5 Extra work.4.6 Possession of site.4.7 Site conditions.5 Direct loss and/or expense.5.1 Introduction.5.2 Direct v indirect.6 Potential heads of claim.6.1 Basic principles.6.2 Two basic claims situations.6.3 Foreshortened programme.6.4 The 'knock-on' effect.6.5 The more common heads of loss.6.6 Cost of a claim.7 Causation.7.1 Theory.7.2 Use of networks.7.3 Float.8 The global approach.9 Substantiation of claims.9.1 Principles.9.2 Nature of supporting evidence.9.3 'Scott Schedule'.PART 2.10 Extension of time under JCT standard form contracts.10.1 Extension of time position under JCT 98.10.2 Extension of time position under IFC 98.10.3 Extension of time position under MW 98.10.4 Extension of time position under WCD 98.10.5 Extension of time position under PCC 98.10.6 Extension of time position under MC 98.10.7 Extension of time position under TC/C 02.10.8 Extension of time position under MPF 03.11 Liquidated damages under JCT standard form contracts.11.1 Liquidated damages position under JCT 98.11.2 Liquidated damages position under IFC 98.11.3 Liquidated damages position under MW 98.11.4 Liquidated damages position under WCD 98.11.5 Liquidated damages position under PCC 98.11.6 Liquidated damages position under MC 98.11.7 Liquidated damages position under TC/C 02.11.8 Liquidated damages position under MPF 03.12 Loss and/or expense under JCT standard form contracts.12.1 Introduction.12.2 Under JCT 98.12.3 Under JCT IFC 98.12.4 Under JCT MW 98.12.5 Under JCT WCD 98.12.6 Under JCT PCC 98.12.7 Under JCT MC 98.12.8 Under JCT TC/C 02.12.9 Under JCT MPF 03.13 Variations.13.1 Introduction.13.2 The baseline.13.3 Bills of quantities.13.4 Functions of the architect and the quantity surveyor.13.5 Variations position under JCT 98.13.6 Variations position under IFC 98.13.7 Variations position under MW 98.13.8 Variations position under WCD 98.13.9 Variations position under PCC 98.13.10 Variations position under MC 98.13.11 Variations position under TC/C 02.13.12 Variations position under MPF 03.PART 3.14 Claims under GC/Works/1 (1998).14.1 Introduction.14.2 Valuation of instructions.14.3 Prolongation and disruption.14.4 Extension of time and liquidated damages.15 Variations and claims under ACA 3.15.1 Introduction.15.2 Monetary claims under ACA 3.15.3 Architect's instructions.15.4 Extension of time and liquidated damages.15.5 Claims on the final certificate.16 Claims under NEC.16.1 Introduction.16.2 Compensation events.16.3 Delay damages.17 Sub-contract claims.17.1 Introduction.17.2 Nominated sub-contract form NSC/C.17.3 Domestic sub-contract form DSC.17.4 Sub-contract conditions for sub-contractors named under IFC 98 (NAM/SC).17.5 The IN/SC form of domestic sub-contract for use with IFC 98.17.6 The Works Contract/2 for use with MC 98.17.7 The ACA form of sub-contract.Appendix A: Example of build up of contractor's entitlement to reimbursement of direct loss and/or expense under JCT 98, clause 26.Appendix B: Extension of time and money claims under DOM/1.Table of cases.Table of standard form contract clauses.Index
Altri titoli varianti Building Contract Claims 4e
Record Nr. UNISA-996214615303316
Chappell David  
Oxford, : Blackwell, 2005
Materiale a stampa
Lo trovi qui: Univ. di Salerno
Opac: Controlla la disponibilità qui
Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell
Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell
Autore Carnell Nicholas J
Edizione [2nd ed.]
Pubbl/distr/stampa Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005
Descrizione fisica 1 online resource (320 p.)
Disciplina 343.41078624
Soggetto topico Construction contracts - England
Breach of contract - England
Time (Law) - England
Construction industry - Management
Soggetto genere / forma Electronic books.
ISBN 1-281-84097-1
9786611840976
0-470-75935-6
0-470-75934-8
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto Contents; Preface; Acknowledgements; List of Abbreviations; 1 Time is Money; 1.1 Introduction; 1.2 An outline of the battlefield - looking forward; 2 Planning the Project; 2.1 Allocating risk; 2.2 Timing obligations; 2.3 Planning tools; 2.4 Information - when and what; 2.5 Getting it right from the outset - contractual obligations; 2.6 The employer's perspective; 3 During the Works; 3.1 Site organisation and reporting systems; 3.2 Notices; 3.3 Monitoring delays; 3.4 Conclusions; 4 Completion Dates; 4.1 Introduction; 4.2 Defining completion; 4.3 Calculating the delay
4.4 Certificates of non-completion4.5 The duty to review; 4.6 Sectional completion; 4.7 The final certificate; 4.8 Time at large; 5 Claim Preparation: Preliminary Considerations; 5.1 Objectives; 5.2 Example in practice; 5.3 Means and ends; 5.4 The legal framework; 6 Legal Considerations; 6.1 When does a dispute become 'legal'?; 6.2 Claims as negotiating tools; 6.3 Showing cause and effect; 6.4 Legal and practical consequences; 7 Analysing the Causes of Delay: Planning and Networks; 7.1 Objectives; 7.2 Strategic planning; 7.3 Project network techniques in programme preparation
7.4 The critical path7.5 Resource analysis; 7.6 Overview; 8 Delay Analysis; 8.1 Introduction; 8.2 Tender and programme analysis; 8.3 Cause and effect; 8.4 Analysing the effect of delays; 8.5 Float; 9 The SCL Protocol; 9.1 Introduction; 9.2 Practical concerns; 9.3 Programme and records; 9.4 Principles relating to delay and compensation; 9.5 Dealing with extensions of time during the project; 9.6 Dealing with disputed extensions of time after the project; 9.7 The PFE Change Management Supplement; 9.8 Some thoughts going forward; 10 Presentation of the Claim; 10.1 General
10.2 Putting together the submission10.3 Presenting the evidence; 10.4 Witnesses of fact; 10.5 Claims consultants; 10.6 Expert evidence; 11 Dispute Resolution; 11.1 Changing times; 11.2 Adjudication; 11.3 Mediation and alternative dispute resolution; Appendix 1 Sample Preliminary Clauses Dealing with Programmes; Appendix 2 Draft Notices of Delay; Notes; Table of Cases; Table of Statutes; Bibliography; Index
Record Nr. UNINA-9910144094703321
Carnell Nicholas J  
Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005
Materiale a stampa
Lo trovi qui: Univ. Federico II
Opac: Controlla la disponibilità qui
Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell
Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell
Autore Carnell Nicholas J
Edizione [2nd ed.]
Pubbl/distr/stampa Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005
Descrizione fisica 1 online resource (320 p.)
Disciplina 343.41078624
Soggetto topico Construction contracts - England
Breach of contract - England
Time (Law) - England
Construction industry - Management
ISBN 1-281-84097-1
9786611840976
0-470-75935-6
0-470-75934-8
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto Contents; Preface; Acknowledgements; List of Abbreviations; 1 Time is Money; 1.1 Introduction; 1.2 An outline of the battlefield - looking forward; 2 Planning the Project; 2.1 Allocating risk; 2.2 Timing obligations; 2.3 Planning tools; 2.4 Information - when and what; 2.5 Getting it right from the outset - contractual obligations; 2.6 The employer's perspective; 3 During the Works; 3.1 Site organisation and reporting systems; 3.2 Notices; 3.3 Monitoring delays; 3.4 Conclusions; 4 Completion Dates; 4.1 Introduction; 4.2 Defining completion; 4.3 Calculating the delay
4.4 Certificates of non-completion4.5 The duty to review; 4.6 Sectional completion; 4.7 The final certificate; 4.8 Time at large; 5 Claim Preparation: Preliminary Considerations; 5.1 Objectives; 5.2 Example in practice; 5.3 Means and ends; 5.4 The legal framework; 6 Legal Considerations; 6.1 When does a dispute become 'legal'?; 6.2 Claims as negotiating tools; 6.3 Showing cause and effect; 6.4 Legal and practical consequences; 7 Analysing the Causes of Delay: Planning and Networks; 7.1 Objectives; 7.2 Strategic planning; 7.3 Project network techniques in programme preparation
7.4 The critical path7.5 Resource analysis; 7.6 Overview; 8 Delay Analysis; 8.1 Introduction; 8.2 Tender and programme analysis; 8.3 Cause and effect; 8.4 Analysing the effect of delays; 8.5 Float; 9 The SCL Protocol; 9.1 Introduction; 9.2 Practical concerns; 9.3 Programme and records; 9.4 Principles relating to delay and compensation; 9.5 Dealing with extensions of time during the project; 9.6 Dealing with disputed extensions of time after the project; 9.7 The PFE Change Management Supplement; 9.8 Some thoughts going forward; 10 Presentation of the Claim; 10.1 General
10.2 Putting together the submission10.3 Presenting the evidence; 10.4 Witnesses of fact; 10.5 Claims consultants; 10.6 Expert evidence; 11 Dispute Resolution; 11.1 Changing times; 11.2 Adjudication; 11.3 Mediation and alternative dispute resolution; Appendix 1 Sample Preliminary Clauses Dealing with Programmes; Appendix 2 Draft Notices of Delay; Notes; Table of Cases; Table of Statutes; Bibliography; Index
Record Nr. UNISA-996203741403316
Carnell Nicholas J  
Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005
Materiale a stampa
Lo trovi qui: Univ. di Salerno
Opac: Controlla la disponibilità qui
Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell
Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell
Autore Carnell Nicholas J
Edizione [2nd ed.]
Pubbl/distr/stampa Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005
Descrizione fisica 1 online resource (320 p.)
Disciplina 343.41078624
Soggetto topico Construction contracts - England
Breach of contract - England
Time (Law) - England
Construction industry - Management
ISBN 1-281-84097-1
9786611840976
0-470-75935-6
0-470-75934-8
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto Contents; Preface; Acknowledgements; List of Abbreviations; 1 Time is Money; 1.1 Introduction; 1.2 An outline of the battlefield - looking forward; 2 Planning the Project; 2.1 Allocating risk; 2.2 Timing obligations; 2.3 Planning tools; 2.4 Information - when and what; 2.5 Getting it right from the outset - contractual obligations; 2.6 The employer's perspective; 3 During the Works; 3.1 Site organisation and reporting systems; 3.2 Notices; 3.3 Monitoring delays; 3.4 Conclusions; 4 Completion Dates; 4.1 Introduction; 4.2 Defining completion; 4.3 Calculating the delay
4.4 Certificates of non-completion4.5 The duty to review; 4.6 Sectional completion; 4.7 The final certificate; 4.8 Time at large; 5 Claim Preparation: Preliminary Considerations; 5.1 Objectives; 5.2 Example in practice; 5.3 Means and ends; 5.4 The legal framework; 6 Legal Considerations; 6.1 When does a dispute become 'legal'?; 6.2 Claims as negotiating tools; 6.3 Showing cause and effect; 6.4 Legal and practical consequences; 7 Analysing the Causes of Delay: Planning and Networks; 7.1 Objectives; 7.2 Strategic planning; 7.3 Project network techniques in programme preparation
7.4 The critical path7.5 Resource analysis; 7.6 Overview; 8 Delay Analysis; 8.1 Introduction; 8.2 Tender and programme analysis; 8.3 Cause and effect; 8.4 Analysing the effect of delays; 8.5 Float; 9 The SCL Protocol; 9.1 Introduction; 9.2 Practical concerns; 9.3 Programme and records; 9.4 Principles relating to delay and compensation; 9.5 Dealing with extensions of time during the project; 9.6 Dealing with disputed extensions of time after the project; 9.7 The PFE Change Management Supplement; 9.8 Some thoughts going forward; 10 Presentation of the Claim; 10.1 General
10.2 Putting together the submission10.3 Presenting the evidence; 10.4 Witnesses of fact; 10.5 Claims consultants; 10.6 Expert evidence; 11 Dispute Resolution; 11.1 Changing times; 11.2 Adjudication; 11.3 Mediation and alternative dispute resolution; Appendix 1 Sample Preliminary Clauses Dealing with Programmes; Appendix 2 Draft Notices of Delay; Notes; Table of Cases; Table of Statutes; Bibliography; Index
Record Nr. UNINA-9910830484503321
Carnell Nicholas J  
Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005
Materiale a stampa
Lo trovi qui: Univ. Federico II
Opac: Controlla la disponibilità qui
Causation and delay in construction disputes / / Nicholas J. Carnell
Causation and delay in construction disputes / / Nicholas J. Carnell
Autore Carnell Nicholas J
Edizione [2nd ed.]
Pubbl/distr/stampa Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005
Descrizione fisica 1 online resource (320 p.)
Disciplina 343.73/078624
Soggetto topico Construction contracts - England
Breach of contract - England
Time (Law) - England
Construction industry - Management
ISBN 1-281-84097-1
9786611840976
0-470-75935-6
0-470-75934-8
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto Contents; Preface; Acknowledgements; List of Abbreviations; 1 Time is Money; 1.1 Introduction; 1.2 An outline of the battlefield - looking forward; 2 Planning the Project; 2.1 Allocating risk; 2.2 Timing obligations; 2.3 Planning tools; 2.4 Information - when and what; 2.5 Getting it right from the outset - contractual obligations; 2.6 The employer's perspective; 3 During the Works; 3.1 Site organisation and reporting systems; 3.2 Notices; 3.3 Monitoring delays; 3.4 Conclusions; 4 Completion Dates; 4.1 Introduction; 4.2 Defining completion; 4.3 Calculating the delay
4.4 Certificates of non-completion4.5 The duty to review; 4.6 Sectional completion; 4.7 The final certificate; 4.8 Time at large; 5 Claim Preparation: Preliminary Considerations; 5.1 Objectives; 5.2 Example in practice; 5.3 Means and ends; 5.4 The legal framework; 6 Legal Considerations; 6.1 When does a dispute become 'legal'?; 6.2 Claims as negotiating tools; 6.3 Showing cause and effect; 6.4 Legal and practical consequences; 7 Analysing the Causes of Delay: Planning and Networks; 7.1 Objectives; 7.2 Strategic planning; 7.3 Project network techniques in programme preparation
7.4 The critical path7.5 Resource analysis; 7.6 Overview; 8 Delay Analysis; 8.1 Introduction; 8.2 Tender and programme analysis; 8.3 Cause and effect; 8.4 Analysing the effect of delays; 8.5 Float; 9 The SCL Protocol; 9.1 Introduction; 9.2 Practical concerns; 9.3 Programme and records; 9.4 Principles relating to delay and compensation; 9.5 Dealing with extensions of time during the project; 9.6 Dealing with disputed extensions of time after the project; 9.7 The PFE Change Management Supplement; 9.8 Some thoughts going forward; 10 Presentation of the Claim; 10.1 General
10.2 Putting together the submission10.3 Presenting the evidence; 10.4 Witnesses of fact; 10.5 Claims consultants; 10.6 Expert evidence; 11 Dispute Resolution; 11.1 Changing times; 11.2 Adjudication; 11.3 Mediation and alternative dispute resolution; Appendix 1 Sample Preliminary Clauses Dealing with Programmes; Appendix 2 Draft Notices of Delay; Notes; Table of Cases; Table of Statutes; Bibliography; Index
Record Nr. UNINA-9910877056503321
Carnell Nicholas J  
Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005
Materiale a stampa
Lo trovi qui: Univ. Federico II
Opac: Controlla la disponibilità qui
Defective construction work [[electronic resource] /] / Kevin Barrett
Defective construction work [[electronic resource] /] / Kevin Barrett
Autore Barrett Kevin
Pubbl/distr/stampa Chichester, West Sussex, UK ; ; Ames, Iowa, : Blackwell Science, c2008
Descrizione fisica 1 online resource (224 p.)
Disciplina 343.42
343.42/07869
624
Soggetto topico Construction contracts - England
Liability for building accidents - England
Premises liability - England
ISBN 1-282-00932-X
9786612009327
1-4443-0236-1
1-4443-0237-X
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto Contents; Preface; Abbreviations; Chapter 1: Definition and Categorisation of Defects; 1.1 Definition of 'defect'; 1.2 Qualitative defects; 1.3 Patent/latent defects; 1.4 Reasonable examination; 1.5 Importance of the distinction between patent and latent defects; 1.6 The 'purchaser', the 'project team' and other terminology; Chapter 2: Common Law, Statutory and Contractual Rights; 2.1 Common law; 2.2 Statute; 2.3 Contractual rights; Chapter 3: Contracts: An Overview; 3.1 Function; 3.2 The basics; 3.3 Express terms; 3.4 Implied terms; 3.5 Exclusion of implied terms; 3.6 Exclusion clauses
3.7 Risk allocation3.8 Model conditions of contract; Chapter 4: No Contract/Restitution; 4.1 Restitution; 4.2 Restitution and defects; Chapter 5: Letters of Intent; 5.1 Function; 5.2 Legal analysis; 5.3 The implications where defects occur; Chapter 6: Tort: An Overview; 6.1 Negligence; 6.2 Complex structures; 6.3 Economic harm; 6.4 Builders and professional consultants; Chapter 7: The Defective Premises Act 1972; 7.1 Application; 7.2 Fitness for habitation; 7.3 Exclusion; Chapter 8: Third Party Rights; 8.1 The exception; 8.2 Agency; 8.3 Assignment; 8.4 Novation
8.5 Statutory third party rights8.6 Collateral contracts; 8.7 Tort; Chapter 9: Statutory Requirements; 9.1 The Building Act 1984; 9.2 Building regulations; 9.3 Construction products; 9.4 Workplace safety regulations; 9.5 CDM regulations; 9.6 The relationship with contractual obligations; Chapter 10: The Builder's Obligations: Design, Workmanship and Materials; 10.1 Buildability, durability and maintenance; 10.2 Workmanship; 10.3 Materials; 10.4 Design; Chapter 11: The Builder's Obligations: Defects Before Completion; 11.1 Temporary disconformities; 11.2 Opening up the work
11.3 Defects and interim paymentChapter 12: The Builder's Obligations: Defects at Completion; 12.1 Scope of work to be completed; 12.2 Completion; 12.3 Snagging; 12.4 The effect of practical completion; 12.5 The ICE, NEC3 and MF/1 conditions; 12.6 The JCT Major Project Construction Contract; 12.7 The provision of information prior to practical completion; Chapter 13: The Builder's Obligations: Defects Post Completion; 13.1 The common law; 13.2 Defects liability period; 13.3 Retention money; 13.4 Retention bonds; 13.5 Final certificates; Chapter 14: The Professional Team
14.1 Membership of a professional body14.2 The structure of the team; 14.3 Duties; 14.4 Buildability, durability and maintenance; Chapter 15: Architects and Engineers; 15.1 Design; 15.2 Selecting builders and other specialists; 15.3 Supervision; 15.4 Periodic inspection; 15.5 Certification; 15.6 Design review; 15.7 Defects investigations; 15.8 Honest reporting; 15.9 Termination of performance; Chapter 16: Project Managers, Surveyors and Others; 16.1 Project managers; 16.2 Quantity surveyors; 16.3 CDM coordinators; 16.4 Clerk of works/engineer's representative; Chapter 17: Compensation
17.1 Abatement
Record Nr. UNISA-996208656303316
Barrett Kevin  
Chichester, West Sussex, UK ; ; Ames, Iowa, : Blackwell Science, c2008
Materiale a stampa
Lo trovi qui: Univ. di Salerno
Opac: Controlla la disponibilità qui
Defective construction work [[electronic resource] /] / Kevin Barrett
Defective construction work [[electronic resource] /] / Kevin Barrett
Autore Barrett Kevin
Pubbl/distr/stampa Chichester, West Sussex, UK ; ; Ames, Iowa, : Blackwell Science, c2008
Descrizione fisica 1 online resource (224 p.)
Disciplina 343.42
343.42/07869
624
Soggetto topico Construction contracts - England
Liability for building accidents - England
Premises liability - England
ISBN 1-282-00932-X
9786612009327
1-4443-0236-1
1-4443-0237-X
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto Contents; Preface; Abbreviations; Chapter 1: Definition and Categorisation of Defects; 1.1 Definition of 'defect'; 1.2 Qualitative defects; 1.3 Patent/latent defects; 1.4 Reasonable examination; 1.5 Importance of the distinction between patent and latent defects; 1.6 The 'purchaser', the 'project team' and other terminology; Chapter 2: Common Law, Statutory and Contractual Rights; 2.1 Common law; 2.2 Statute; 2.3 Contractual rights; Chapter 3: Contracts: An Overview; 3.1 Function; 3.2 The basics; 3.3 Express terms; 3.4 Implied terms; 3.5 Exclusion of implied terms; 3.6 Exclusion clauses
3.7 Risk allocation3.8 Model conditions of contract; Chapter 4: No Contract/Restitution; 4.1 Restitution; 4.2 Restitution and defects; Chapter 5: Letters of Intent; 5.1 Function; 5.2 Legal analysis; 5.3 The implications where defects occur; Chapter 6: Tort: An Overview; 6.1 Negligence; 6.2 Complex structures; 6.3 Economic harm; 6.4 Builders and professional consultants; Chapter 7: The Defective Premises Act 1972; 7.1 Application; 7.2 Fitness for habitation; 7.3 Exclusion; Chapter 8: Third Party Rights; 8.1 The exception; 8.2 Agency; 8.3 Assignment; 8.4 Novation
8.5 Statutory third party rights8.6 Collateral contracts; 8.7 Tort; Chapter 9: Statutory Requirements; 9.1 The Building Act 1984; 9.2 Building regulations; 9.3 Construction products; 9.4 Workplace safety regulations; 9.5 CDM regulations; 9.6 The relationship with contractual obligations; Chapter 10: The Builder's Obligations: Design, Workmanship and Materials; 10.1 Buildability, durability and maintenance; 10.2 Workmanship; 10.3 Materials; 10.4 Design; Chapter 11: The Builder's Obligations: Defects Before Completion; 11.1 Temporary disconformities; 11.2 Opening up the work
11.3 Defects and interim paymentChapter 12: The Builder's Obligations: Defects at Completion; 12.1 Scope of work to be completed; 12.2 Completion; 12.3 Snagging; 12.4 The effect of practical completion; 12.5 The ICE, NEC3 and MF/1 conditions; 12.6 The JCT Major Project Construction Contract; 12.7 The provision of information prior to practical completion; Chapter 13: The Builder's Obligations: Defects Post Completion; 13.1 The common law; 13.2 Defects liability period; 13.3 Retention money; 13.4 Retention bonds; 13.5 Final certificates; Chapter 14: The Professional Team
14.1 Membership of a professional body14.2 The structure of the team; 14.3 Duties; 14.4 Buildability, durability and maintenance; Chapter 15: Architects and Engineers; 15.1 Design; 15.2 Selecting builders and other specialists; 15.3 Supervision; 15.4 Periodic inspection; 15.5 Certification; 15.6 Design review; 15.7 Defects investigations; 15.8 Honest reporting; 15.9 Termination of performance; Chapter 16: Project Managers, Surveyors and Others; 16.1 Project managers; 16.2 Quantity surveyors; 16.3 CDM coordinators; 16.4 Clerk of works/engineer's representative; Chapter 17: Compensation
17.1 Abatement
Record Nr. UNINA-9910145832203321
Barrett Kevin  
Chichester, West Sussex, UK ; ; Ames, Iowa, : Blackwell Science, c2008
Materiale a stampa
Lo trovi qui: Univ. Federico II
Opac: Controlla la disponibilità qui
Defective construction work [[electronic resource] /] / Kevin Barrett
Defective construction work [[electronic resource] /] / Kevin Barrett
Autore Barrett Kevin
Pubbl/distr/stampa Chichester, West Sussex, UK ; ; Ames, Iowa, : Blackwell Science, c2008
Descrizione fisica 1 online resource (224 p.)
Disciplina 343.42
343.42/07869
624
Soggetto topico Construction contracts - England
Liability for building accidents - England
Premises liability - England
ISBN 1-282-00932-X
9786612009327
1-4443-0236-1
1-4443-0237-X
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto Contents; Preface; Abbreviations; Chapter 1: Definition and Categorisation of Defects; 1.1 Definition of 'defect'; 1.2 Qualitative defects; 1.3 Patent/latent defects; 1.4 Reasonable examination; 1.5 Importance of the distinction between patent and latent defects; 1.6 The 'purchaser', the 'project team' and other terminology; Chapter 2: Common Law, Statutory and Contractual Rights; 2.1 Common law; 2.2 Statute; 2.3 Contractual rights; Chapter 3: Contracts: An Overview; 3.1 Function; 3.2 The basics; 3.3 Express terms; 3.4 Implied terms; 3.5 Exclusion of implied terms; 3.6 Exclusion clauses
3.7 Risk allocation3.8 Model conditions of contract; Chapter 4: No Contract/Restitution; 4.1 Restitution; 4.2 Restitution and defects; Chapter 5: Letters of Intent; 5.1 Function; 5.2 Legal analysis; 5.3 The implications where defects occur; Chapter 6: Tort: An Overview; 6.1 Negligence; 6.2 Complex structures; 6.3 Economic harm; 6.4 Builders and professional consultants; Chapter 7: The Defective Premises Act 1972; 7.1 Application; 7.2 Fitness for habitation; 7.3 Exclusion; Chapter 8: Third Party Rights; 8.1 The exception; 8.2 Agency; 8.3 Assignment; 8.4 Novation
8.5 Statutory third party rights8.6 Collateral contracts; 8.7 Tort; Chapter 9: Statutory Requirements; 9.1 The Building Act 1984; 9.2 Building regulations; 9.3 Construction products; 9.4 Workplace safety regulations; 9.5 CDM regulations; 9.6 The relationship with contractual obligations; Chapter 10: The Builder's Obligations: Design, Workmanship and Materials; 10.1 Buildability, durability and maintenance; 10.2 Workmanship; 10.3 Materials; 10.4 Design; Chapter 11: The Builder's Obligations: Defects Before Completion; 11.1 Temporary disconformities; 11.2 Opening up the work
11.3 Defects and interim paymentChapter 12: The Builder's Obligations: Defects at Completion; 12.1 Scope of work to be completed; 12.2 Completion; 12.3 Snagging; 12.4 The effect of practical completion; 12.5 The ICE, NEC3 and MF/1 conditions; 12.6 The JCT Major Project Construction Contract; 12.7 The provision of information prior to practical completion; Chapter 13: The Builder's Obligations: Defects Post Completion; 13.1 The common law; 13.2 Defects liability period; 13.3 Retention money; 13.4 Retention bonds; 13.5 Final certificates; Chapter 14: The Professional Team
14.1 Membership of a professional body14.2 The structure of the team; 14.3 Duties; 14.4 Buildability, durability and maintenance; Chapter 15: Architects and Engineers; 15.1 Design; 15.2 Selecting builders and other specialists; 15.3 Supervision; 15.4 Periodic inspection; 15.5 Certification; 15.6 Design review; 15.7 Defects investigations; 15.8 Honest reporting; 15.9 Termination of performance; Chapter 16: Project Managers, Surveyors and Others; 16.1 Project managers; 16.2 Quantity surveyors; 16.3 CDM coordinators; 16.4 Clerk of works/engineer's representative; Chapter 17: Compensation
17.1 Abatement
Record Nr. UNINA-9910830047903321
Barrett Kevin  
Chichester, West Sussex, UK ; ; Ames, Iowa, : Blackwell Science, c2008
Materiale a stampa
Lo trovi qui: Univ. Federico II
Opac: Controlla la disponibilità qui
Defective construction work / / Kevin Barrett
Defective construction work / / Kevin Barrett
Autore Barrett Kevin
Pubbl/distr/stampa Chichester, West Sussex, UK ; ; Ames, Iowa, : Blackwell Science, c2008
Descrizione fisica 1 online resource (224 p.)
Disciplina 343.42
343.42/07869
624
Soggetto topico Construction contracts - England
Liability for building accidents - England
Premises liability - England
ISBN 1-282-00932-X
9786612009327
1-4443-0236-1
1-4443-0237-X
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto Contents; Preface; Abbreviations; Chapter 1: Definition and Categorisation of Defects; 1.1 Definition of 'defect'; 1.2 Qualitative defects; 1.3 Patent/latent defects; 1.4 Reasonable examination; 1.5 Importance of the distinction between patent and latent defects; 1.6 The 'purchaser', the 'project team' and other terminology; Chapter 2: Common Law, Statutory and Contractual Rights; 2.1 Common law; 2.2 Statute; 2.3 Contractual rights; Chapter 3: Contracts: An Overview; 3.1 Function; 3.2 The basics; 3.3 Express terms; 3.4 Implied terms; 3.5 Exclusion of implied terms; 3.6 Exclusion clauses
3.7 Risk allocation3.8 Model conditions of contract; Chapter 4: No Contract/Restitution; 4.1 Restitution; 4.2 Restitution and defects; Chapter 5: Letters of Intent; 5.1 Function; 5.2 Legal analysis; 5.3 The implications where defects occur; Chapter 6: Tort: An Overview; 6.1 Negligence; 6.2 Complex structures; 6.3 Economic harm; 6.4 Builders and professional consultants; Chapter 7: The Defective Premises Act 1972; 7.1 Application; 7.2 Fitness for habitation; 7.3 Exclusion; Chapter 8: Third Party Rights; 8.1 The exception; 8.2 Agency; 8.3 Assignment; 8.4 Novation
8.5 Statutory third party rights8.6 Collateral contracts; 8.7 Tort; Chapter 9: Statutory Requirements; 9.1 The Building Act 1984; 9.2 Building regulations; 9.3 Construction products; 9.4 Workplace safety regulations; 9.5 CDM regulations; 9.6 The relationship with contractual obligations; Chapter 10: The Builder's Obligations: Design, Workmanship and Materials; 10.1 Buildability, durability and maintenance; 10.2 Workmanship; 10.3 Materials; 10.4 Design; Chapter 11: The Builder's Obligations: Defects Before Completion; 11.1 Temporary disconformities; 11.2 Opening up the work
11.3 Defects and interim paymentChapter 12: The Builder's Obligations: Defects at Completion; 12.1 Scope of work to be completed; 12.2 Completion; 12.3 Snagging; 12.4 The effect of practical completion; 12.5 The ICE, NEC3 and MF/1 conditions; 12.6 The JCT Major Project Construction Contract; 12.7 The provision of information prior to practical completion; Chapter 13: The Builder's Obligations: Defects Post Completion; 13.1 The common law; 13.2 Defects liability period; 13.3 Retention money; 13.4 Retention bonds; 13.5 Final certificates; Chapter 14: The Professional Team
14.1 Membership of a professional body14.2 The structure of the team; 14.3 Duties; 14.4 Buildability, durability and maintenance; Chapter 15: Architects and Engineers; 15.1 Design; 15.2 Selecting builders and other specialists; 15.3 Supervision; 15.4 Periodic inspection; 15.5 Certification; 15.6 Design review; 15.7 Defects investigations; 15.8 Honest reporting; 15.9 Termination of performance; Chapter 16: Project Managers, Surveyors and Others; 16.1 Project managers; 16.2 Quantity surveyors; 16.3 CDM coordinators; 16.4 Clerk of works/engineer's representative; Chapter 17: Compensation
17.1 Abatement
Record Nr. UNINA-9910876792203321
Barrett Kevin  
Chichester, West Sussex, UK ; ; Ames, Iowa, : Blackwell Science, c2008
Materiale a stampa
Lo trovi qui: Univ. Federico II
Opac: Controlla la disponibilità qui
The JCT 05 standard building sub-contract [[electronic resource] /] / Peter Barnes
The JCT 05 standard building sub-contract [[electronic resource] /] / Peter Barnes
Autore Barnes Peter
Edizione [1st ed.]
Pubbl/distr/stampa Boston, : Blackwell Pub., c2006
Descrizione fisica 1 online resource (386 p.)
Disciplina 343.4107869
692.80941
Soggetto topico Construction contracts - England
Construction industry - Subcontracting - England
Soggetto genere / forma Electronic books.
ISBN 1-280-74878-8
9786610748785
0-470-76412-0
0-470-75970-4
1-4051-7267-3
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto The JCT 05 Standard Building Sub-Contract; Contents; Preface; Definitions; 1 Background and Introduction; The purpose and use of the JCT Standard Building Sub-Contract; Sub-contracting generally; Letters of intent; Standard forms of contract and sub-contract; 2 SBCSub/A and SBCSub/D/A; The JCT Standard Building Sub-Contract Agreement (SBCSub/A or SBCSub/D/A) - introduction; The structure of SBCSub/A and SBCSub/D/A; The recitals; The articles; The sub-contract particulars; Summary of interim and final payment provisions; Attestation forms; Schedule of information
Notes (to annexures to the agreement and to the schedule of information)Supplementary particulars (containing information needed for formula adjustment); 3 Definitions and Interpretations; The JCT Standard Building Sub-Contract Conditions (SBCSub/C or SBCSub/D/C): section 1 (including clauses 1.1 to 1.10 of SBCSub/C and SBCSub/D/C); General; Section 1 - definitions and interpretation; 4 Sub-Contractor's Obligations; SBCSub/C and SBCSub/D/C: Section 2 - carrying out the sub-contract works (clauses 2.1, 2.2, 2.4 to 2.15 inclusive and schedule 5- contractor's design submission procedure)
Sub-contractor's obligationsSupply of documents, setting out, etc.; Errors, discrepancies and divergencies; Sub-contractor's design portion (SCDP) design work; Unfixed materials and goods; 5 Time; SBCSub/C and SBCSub/D/C: section 2 - carrying out the sub-contract works (clauses 2.3, 2.16 to 2.21 inclusive); Sub-contractor's obligations; Adjustment of period for completion; Practical completion and lateness; 6 Defects, Design Documents and Warranties; SBCSub/C and SBCSub/D/C: section 2 - carrying out the sub-contract works (clauses 2.22 to 2.26 inclusive); Defects
Sub-contractor's design documentsCollateral warranties; 7 Control of the Sub-Contract Works; SBCSub/C and SBCSub/D/C: section 3 - control of the sub-contract works (and schedule 1 sub-contract code of practice); Assignment and sub-letting; Contractor's directions; Opening up and remedial measures; Attendance and site conduct; Health and safety and CDM requirements; Suspension of main contract by contractor; Other provisions; 8 Payment; SBCSub/C and SBCSub/D/C: section 4 - payment (clauses 4.1 to 4.18 inclusive; schedule 3 forms of bonds; and schedule 4 fluctuations options)
Payment - generallySub-contract sum and sub-contract tender sum; Payments; Gross valuation; Retention; Discount; The final payment; Counterclaim, set-off and abatement; The payment notice; The withholding notice; Timing of payments, payment notices and withholding notices; Interest; Sub-contractor's right of suspension; Fluctuation options; 9 Loss and Expense; SBCSub/C and SBCSub/D/C: section 4 - payment (clauses 4.19 to 4.22 inclusive; Introduction; Loss and expense; Potential heads of claim for a loss and expense claim
Common law damages claims (in respect of a breach of contract) (reservation of rights and remedies of contractor and sub-contractor)
Record Nr. UNINA-9910143321703321
Barnes Peter  
Boston, : Blackwell Pub., c2006
Materiale a stampa
Lo trovi qui: Univ. Federico II
Opac: Controlla la disponibilità qui