top

  Info

  • Utilizzare la checkbox di selezione a fianco di ciascun documento per attivare le funzionalità di stampa, invio email, download nei formati disponibili del (i) record.

  Info

  • Utilizzare questo link per rimuovere la selezione effettuata.
Building contract claims [[electronic resource]]
Building contract claims [[electronic resource]]
Autore Chappell David
Edizione [4th ed. /]
Pubbl/distr/stampa Oxford, : Blackwell, 2005
Descrizione fisica 1 online resource (xi, 552 p. ) : ill
Disciplina 343.41078624
Altri autori (Persone) Powell-SmithVincent
SimsJohn <1929->
ChappellDavid
Soggetto topico Construction contracts - Great Britain
Breach of contract - Great Britain
Actions and defenses - Great Britain
Damages - Great Britain
Law
Construction contracts - England
Breach of contract - England
Actions and defenses - England
Damages - England
Law - Great Britain
Law - Non-U.S
Law, Politics & Government
Soggetto genere / forma Electronic books.
ISBN 1-280-21296-9
9786610212965
0-470-79917-X
0-470-75932-1
1-4051-4808-X
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto PART 1.1 Introduction.1.1 Structure of the book.1.2 Definitions.1.3 The basis of claims.1.4 Architect's and Contract Administrator's powers and liability to the contractor.1.5 Quantity surveyor's powers.2 Time.2.1 Time of the essence.2.2 Time at large.2.3 Extension of time clauses in contracts.2.4 Concurrency.2.5 Acceleration.2.6 Sectional completion.2.7 The SCL extension of time protocol.3 Liquidated damages.3.1 The meaning and purpose of liquidated damages.3.2 Liquidated damages or penalty.3.3 Liquidated damages as limitation of liability.3.4 Sums greater than a genuine pre-estimate.3.5 Liquidated damages as an exhaustive remedy.3.6 Injunction.3.7 Liquidated damages in relation to loss.3.8 Where there is no breach of contract.3.9 Calculation of liquidated damages.3.10 Maximum recovery if sum is a penalty.3.11 Maximum recovery if liquidated damages do not apply.3.12 Bonus clauses.4 Basis for common law claims.4.1 General.4.2 Implied terms in building contracts.4.3 Variation of contract.4.4 Omission of work to give it to others.4.5 Extra work.4.6 Possession of site.4.7 Site conditions.5 Direct loss and/or expense.5.1 Introduction.5.2 Direct v indirect.6 Potential heads of claim.6.1 Basic principles.6.2 Two basic claims situations.6.3 Foreshortened programme.6.4 The 'knock-on' effect.6.5 The more common heads of loss.6.6 Cost of a claim.7 Causation.7.1 Theory.7.2 Use of networks.7.3 Float.8 The global approach.9 Substantiation of claims.9.1 Principles.9.2 Nature of supporting evidence.9.3 'Scott Schedule'.PART 2.10 Extension of time under JCT standard form contracts.10.1 Extension of time position under JCT 98.10.2 Extension of time position under IFC 98.10.3 Extension of time position under MW 98.10.4 Extension of time position under WCD 98.10.5 Extension of time position under PCC 98.10.6 Extension of time position under MC 98.10.7 Extension of time position under TC/C 02.10.8 Extension of time position under MPF 03.11 Liquidated damages under JCT standard form contracts.11.1 Liquidated damages position under JCT 98.11.2 Liquidated damages position under IFC 98.11.3 Liquidated damages position under MW 98.11.4 Liquidated damages position under WCD 98.11.5 Liquidated damages position under PCC 98.11.6 Liquidated damages position under MC 98.11.7 Liquidated damages position under TC/C 02.11.8 Liquidated damages position under MPF 03.12 Loss and/or expense under JCT standard form contracts.12.1 Introduction.12.2 Under JCT 98.12.3 Under JCT IFC 98.12.4 Under JCT MW 98.12.5 Under JCT WCD 98.12.6 Under JCT PCC 98.12.7 Under JCT MC 98.12.8 Under JCT TC/C 02.12.9 Under JCT MPF 03.13 Variations.13.1 Introduction.13.2 The baseline.13.3 Bills of quantities.13.4 Functions of the architect and the quantity surveyor.13.5 Variations position under JCT 98.13.6 Variations position under IFC 98.13.7 Variations position under MW 98.13.8 Variations position under WCD 98.13.9 Variations position under PCC 98.13.10 Variations position under MC 98.13.11 Variations position under TC/C 02.13.12 Variations position under MPF 03.PART 3.14 Claims under GC/Works/1 (1998).14.1 Introduction.14.2 Valuation of instructions.14.3 Prolongation and disruption.14.4 Extension of time and liquidated damages.15 Variations and claims under ACA 3.15.1 Introduction.15.2 Monetary claims under ACA 3.15.3 Architect's instructions.15.4 Extension of time and liquidated damages.15.5 Claims on the final certificate.16 Claims under NEC.16.1 Introduction.16.2 Compensation events.16.3 Delay damages.17 Sub-contract claims.17.1 Introduction.17.2 Nominated sub-contract form NSC/C.17.3 Domestic sub-contract form DSC.17.4 Sub-contract conditions for sub-contractors named under IFC 98 (NAM/SC).17.5 The IN/SC form of domestic sub-contract for use with IFC 98.17.6 The Works Contract/2 for use with MC 98.17.7 The ACA form of sub-contract.Appendix A: Example of build up of contractor's entitlement to reimbursement of direct loss and/or expense under JCT 98, clause 26.Appendix B: Extension of time and money claims under DOM/1.Table of cases.Table of standard form contract clauses.Index
Altri titoli varianti Building Contract Claims 4e
Record Nr. UNISA-996214615303316
Chappell David  
Oxford, : Blackwell, 2005
Materiale a stampa
Lo trovi qui: Univ. di Salerno
Opac: Controlla la disponibilità qui
The Case of John Coombes, Valentine Houseman, and Edward Pearce [[electronic resource]]
The Case of John Coombes, Valentine Houseman, and Edward Pearce [[electronic resource]]
Pubbl/distr/stampa [London, : s.n., 1682?]
Descrizione fisica 1 sheet ([1] p.)
Soggetto topico Breach of contract - England
Debtor and creditor - England
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Record Nr. UNISA-996397259403316
[London, : s.n., 1682?]
Materiale a stampa
Lo trovi qui: Univ. di Salerno
Opac: Controlla la disponibilità qui
The Case of John Coombes, Valentine Houseman, and Edward Pearce [[electronic resource]]
The Case of John Coombes, Valentine Houseman, and Edward Pearce [[electronic resource]]
Pubbl/distr/stampa [S.l., : s.n., 1676]
Descrizione fisica 1 sheet ([1] p.)
Soggetto topico Breach of contract - England
Extinguishment of debts - England
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Record Nr. UNISA-996389745503316
[S.l., : s.n., 1676]
Materiale a stampa
Lo trovi qui: Univ. di Salerno
Opac: Controlla la disponibilità qui
Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell
Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell
Autore Carnell Nicholas J
Edizione [2nd ed.]
Pubbl/distr/stampa Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005
Descrizione fisica 1 online resource (320 p.)
Disciplina 343.41078624
Soggetto topico Construction contracts - England
Breach of contract - England
Time (Law) - England
Construction industry - Management
Soggetto genere / forma Electronic books.
ISBN 1-281-84097-1
9786611840976
0-470-75935-6
0-470-75934-8
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto Contents; Preface; Acknowledgements; List of Abbreviations; 1 Time is Money; 1.1 Introduction; 1.2 An outline of the battlefield - looking forward; 2 Planning the Project; 2.1 Allocating risk; 2.2 Timing obligations; 2.3 Planning tools; 2.4 Information - when and what; 2.5 Getting it right from the outset - contractual obligations; 2.6 The employer's perspective; 3 During the Works; 3.1 Site organisation and reporting systems; 3.2 Notices; 3.3 Monitoring delays; 3.4 Conclusions; 4 Completion Dates; 4.1 Introduction; 4.2 Defining completion; 4.3 Calculating the delay
4.4 Certificates of non-completion4.5 The duty to review; 4.6 Sectional completion; 4.7 The final certificate; 4.8 Time at large; 5 Claim Preparation: Preliminary Considerations; 5.1 Objectives; 5.2 Example in practice; 5.3 Means and ends; 5.4 The legal framework; 6 Legal Considerations; 6.1 When does a dispute become 'legal'?; 6.2 Claims as negotiating tools; 6.3 Showing cause and effect; 6.4 Legal and practical consequences; 7 Analysing the Causes of Delay: Planning and Networks; 7.1 Objectives; 7.2 Strategic planning; 7.3 Project network techniques in programme preparation
7.4 The critical path7.5 Resource analysis; 7.6 Overview; 8 Delay Analysis; 8.1 Introduction; 8.2 Tender and programme analysis; 8.3 Cause and effect; 8.4 Analysing the effect of delays; 8.5 Float; 9 The SCL Protocol; 9.1 Introduction; 9.2 Practical concerns; 9.3 Programme and records; 9.4 Principles relating to delay and compensation; 9.5 Dealing with extensions of time during the project; 9.6 Dealing with disputed extensions of time after the project; 9.7 The PFE Change Management Supplement; 9.8 Some thoughts going forward; 10 Presentation of the Claim; 10.1 General
10.2 Putting together the submission10.3 Presenting the evidence; 10.4 Witnesses of fact; 10.5 Claims consultants; 10.6 Expert evidence; 11 Dispute Resolution; 11.1 Changing times; 11.2 Adjudication; 11.3 Mediation and alternative dispute resolution; Appendix 1 Sample Preliminary Clauses Dealing with Programmes; Appendix 2 Draft Notices of Delay; Notes; Table of Cases; Table of Statutes; Bibliography; Index
Record Nr. UNINA-9910144094703321
Carnell Nicholas J  
Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005
Materiale a stampa
Lo trovi qui: Univ. Federico II
Opac: Controlla la disponibilità qui
Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell
Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell
Autore Carnell Nicholas J
Edizione [2nd ed.]
Pubbl/distr/stampa Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005
Descrizione fisica 1 online resource (320 p.)
Disciplina 343.41078624
Soggetto topico Construction contracts - England
Breach of contract - England
Time (Law) - England
Construction industry - Management
ISBN 1-281-84097-1
9786611840976
0-470-75935-6
0-470-75934-8
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto Contents; Preface; Acknowledgements; List of Abbreviations; 1 Time is Money; 1.1 Introduction; 1.2 An outline of the battlefield - looking forward; 2 Planning the Project; 2.1 Allocating risk; 2.2 Timing obligations; 2.3 Planning tools; 2.4 Information - when and what; 2.5 Getting it right from the outset - contractual obligations; 2.6 The employer's perspective; 3 During the Works; 3.1 Site organisation and reporting systems; 3.2 Notices; 3.3 Monitoring delays; 3.4 Conclusions; 4 Completion Dates; 4.1 Introduction; 4.2 Defining completion; 4.3 Calculating the delay
4.4 Certificates of non-completion4.5 The duty to review; 4.6 Sectional completion; 4.7 The final certificate; 4.8 Time at large; 5 Claim Preparation: Preliminary Considerations; 5.1 Objectives; 5.2 Example in practice; 5.3 Means and ends; 5.4 The legal framework; 6 Legal Considerations; 6.1 When does a dispute become 'legal'?; 6.2 Claims as negotiating tools; 6.3 Showing cause and effect; 6.4 Legal and practical consequences; 7 Analysing the Causes of Delay: Planning and Networks; 7.1 Objectives; 7.2 Strategic planning; 7.3 Project network techniques in programme preparation
7.4 The critical path7.5 Resource analysis; 7.6 Overview; 8 Delay Analysis; 8.1 Introduction; 8.2 Tender and programme analysis; 8.3 Cause and effect; 8.4 Analysing the effect of delays; 8.5 Float; 9 The SCL Protocol; 9.1 Introduction; 9.2 Practical concerns; 9.3 Programme and records; 9.4 Principles relating to delay and compensation; 9.5 Dealing with extensions of time during the project; 9.6 Dealing with disputed extensions of time after the project; 9.7 The PFE Change Management Supplement; 9.8 Some thoughts going forward; 10 Presentation of the Claim; 10.1 General
10.2 Putting together the submission10.3 Presenting the evidence; 10.4 Witnesses of fact; 10.5 Claims consultants; 10.6 Expert evidence; 11 Dispute Resolution; 11.1 Changing times; 11.2 Adjudication; 11.3 Mediation and alternative dispute resolution; Appendix 1 Sample Preliminary Clauses Dealing with Programmes; Appendix 2 Draft Notices of Delay; Notes; Table of Cases; Table of Statutes; Bibliography; Index
Record Nr. UNISA-996203741403316
Carnell Nicholas J  
Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005
Materiale a stampa
Lo trovi qui: Univ. di Salerno
Opac: Controlla la disponibilità qui
Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell
Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell
Autore Carnell Nicholas J
Edizione [2nd ed.]
Pubbl/distr/stampa Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005
Descrizione fisica 1 online resource (320 p.)
Disciplina 343.41078624
Soggetto topico Construction contracts - England
Breach of contract - England
Time (Law) - England
Construction industry - Management
ISBN 1-281-84097-1
9786611840976
0-470-75935-6
0-470-75934-8
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto Contents; Preface; Acknowledgements; List of Abbreviations; 1 Time is Money; 1.1 Introduction; 1.2 An outline of the battlefield - looking forward; 2 Planning the Project; 2.1 Allocating risk; 2.2 Timing obligations; 2.3 Planning tools; 2.4 Information - when and what; 2.5 Getting it right from the outset - contractual obligations; 2.6 The employer's perspective; 3 During the Works; 3.1 Site organisation and reporting systems; 3.2 Notices; 3.3 Monitoring delays; 3.4 Conclusions; 4 Completion Dates; 4.1 Introduction; 4.2 Defining completion; 4.3 Calculating the delay
4.4 Certificates of non-completion4.5 The duty to review; 4.6 Sectional completion; 4.7 The final certificate; 4.8 Time at large; 5 Claim Preparation: Preliminary Considerations; 5.1 Objectives; 5.2 Example in practice; 5.3 Means and ends; 5.4 The legal framework; 6 Legal Considerations; 6.1 When does a dispute become 'legal'?; 6.2 Claims as negotiating tools; 6.3 Showing cause and effect; 6.4 Legal and practical consequences; 7 Analysing the Causes of Delay: Planning and Networks; 7.1 Objectives; 7.2 Strategic planning; 7.3 Project network techniques in programme preparation
7.4 The critical path7.5 Resource analysis; 7.6 Overview; 8 Delay Analysis; 8.1 Introduction; 8.2 Tender and programme analysis; 8.3 Cause and effect; 8.4 Analysing the effect of delays; 8.5 Float; 9 The SCL Protocol; 9.1 Introduction; 9.2 Practical concerns; 9.3 Programme and records; 9.4 Principles relating to delay and compensation; 9.5 Dealing with extensions of time during the project; 9.6 Dealing with disputed extensions of time after the project; 9.7 The PFE Change Management Supplement; 9.8 Some thoughts going forward; 10 Presentation of the Claim; 10.1 General
10.2 Putting together the submission10.3 Presenting the evidence; 10.4 Witnesses of fact; 10.5 Claims consultants; 10.6 Expert evidence; 11 Dispute Resolution; 11.1 Changing times; 11.2 Adjudication; 11.3 Mediation and alternative dispute resolution; Appendix 1 Sample Preliminary Clauses Dealing with Programmes; Appendix 2 Draft Notices of Delay; Notes; Table of Cases; Table of Statutes; Bibliography; Index
Record Nr. UNINA-9910830484503321
Carnell Nicholas J  
Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005
Materiale a stampa
Lo trovi qui: Univ. Federico II
Opac: Controlla la disponibilità qui
Causation and delay in construction disputes / / Nicholas J. Carnell
Causation and delay in construction disputes / / Nicholas J. Carnell
Autore Carnell Nicholas J
Edizione [2nd ed.]
Pubbl/distr/stampa Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005
Descrizione fisica 1 online resource (320 p.)
Disciplina 343.73/078624
Soggetto topico Construction contracts - England
Breach of contract - England
Time (Law) - England
Construction industry - Management
ISBN 9786611840976
9781281840974
1281840971
9780470759356
0470759356
9780470759349
0470759348
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto Contents; Preface; Acknowledgements; List of Abbreviations; 1 Time is Money; 1.1 Introduction; 1.2 An outline of the battlefield - looking forward; 2 Planning the Project; 2.1 Allocating risk; 2.2 Timing obligations; 2.3 Planning tools; 2.4 Information - when and what; 2.5 Getting it right from the outset - contractual obligations; 2.6 The employer's perspective; 3 During the Works; 3.1 Site organisation and reporting systems; 3.2 Notices; 3.3 Monitoring delays; 3.4 Conclusions; 4 Completion Dates; 4.1 Introduction; 4.2 Defining completion; 4.3 Calculating the delay
4.4 Certificates of non-completion4.5 The duty to review; 4.6 Sectional completion; 4.7 The final certificate; 4.8 Time at large; 5 Claim Preparation: Preliminary Considerations; 5.1 Objectives; 5.2 Example in practice; 5.3 Means and ends; 5.4 The legal framework; 6 Legal Considerations; 6.1 When does a dispute become 'legal'?; 6.2 Claims as negotiating tools; 6.3 Showing cause and effect; 6.4 Legal and practical consequences; 7 Analysing the Causes of Delay: Planning and Networks; 7.1 Objectives; 7.2 Strategic planning; 7.3 Project network techniques in programme preparation
7.4 The critical path7.5 Resource analysis; 7.6 Overview; 8 Delay Analysis; 8.1 Introduction; 8.2 Tender and programme analysis; 8.3 Cause and effect; 8.4 Analysing the effect of delays; 8.5 Float; 9 The SCL Protocol; 9.1 Introduction; 9.2 Practical concerns; 9.3 Programme and records; 9.4 Principles relating to delay and compensation; 9.5 Dealing with extensions of time during the project; 9.6 Dealing with disputed extensions of time after the project; 9.7 The PFE Change Management Supplement; 9.8 Some thoughts going forward; 10 Presentation of the Claim; 10.1 General
10.2 Putting together the submission10.3 Presenting the evidence; 10.4 Witnesses of fact; 10.5 Claims consultants; 10.6 Expert evidence; 11 Dispute Resolution; 11.1 Changing times; 11.2 Adjudication; 11.3 Mediation and alternative dispute resolution; Appendix 1 Sample Preliminary Clauses Dealing with Programmes; Appendix 2 Draft Notices of Delay; Notes; Table of Cases; Table of Statutes; Bibliography; Index
Record Nr. UNINA-9911019651703321
Carnell Nicholas J  
Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005
Materiale a stampa
Lo trovi qui: Univ. Federico II
Opac: Controlla la disponibilità qui
Foreign currency : claims, judgments, and damages / / Michael Howard, John Knott, John Kimbell
Foreign currency : claims, judgments, and damages / / Michael Howard, John Knott, John Kimbell
Autore Knott John (Writer on law)
Edizione [First edition.]
Pubbl/distr/stampa Abingdon, Oxon : , : Informa Law from Routledge, , 2016
Descrizione fisica 1 online resource (392 pages)
Disciplina 343.42/032
343.42032
Altri autori (Persone) HowardM. N (Michael Newman)
KimbellJohn A (John Ashley)
Collana Lloyd's Commercial Law Library
Soggetto topico Foreign exchange - Law and legislation - England
Damages - England
Breach of contract - England
Torts - England
ISBN 9781317659280
1317659287
9781315766058
1315766051
9781317659297
1317659295
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto ch. 1. Introduction -- ch. 2. Basic concepts -- ch. 3. Sterling : its historical role, and the decline that led to a change in the law -- ch. 4. The Euro zone -- ch. 5. The change in English law introduced by Miliangos and its forebears -- ch. 6. Contract -- ch. 7. Tort -- ch. 8. Restitution and unjust enrichment -- ch. 9. The law of trusts and fiduciaries -- ch. 10. Claims against limited or common funds -- ch. 11. Set-off -- ch. 12. Interest -- ch. 13. Are currency exchange losses recoverable as damages? -- ch. 14. Procedure and evidence -- ch. 15. Fiat money, legal tender and alternative money.
Record Nr. UNINA-9910149440203321
Knott John (Writer on law)  
Abingdon, Oxon : , : Informa Law from Routledge, , 2016
Materiale a stampa
Lo trovi qui: Univ. Federico II
Opac: Controlla la disponibilità qui
Liquidated damages and extensions of time in construction contracts [[electronic resource] /] / Brian Eggleston
Liquidated damages and extensions of time in construction contracts [[electronic resource] /] / Brian Eggleston
Autore Eggleston Brian, CEng
Edizione [3rd ed.]
Pubbl/distr/stampa Chichester, U.K. ; ; Ames, Iowa, : Wiley-Blackwell Pub., 2009
Descrizione fisica 1 online resource (406 p.)
Disciplina 343.41
343.41/078624
Soggetto topico Construction contracts - England
Performance (Law) - England
Breach of contract - England
Damages - England
Time (Law) - England
Construction contracts - Wales
Performance (Law) - Wales
Breach of contract - Wales
Damages - Wales
Time (Law) - Wales
Soggetto genere / forma Electronic books.
ISBN 1-282-03455-3
9786612034558
1-4443-0162-4
1-4443-0163-2
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto Contents; Preface to Third Edition; References; Acknowledgements; Chapter 1: Introduction; 1.1 General overview; 1.2 Legal developments; 1.3 Contractual developments; Chapter 2: Time in contracts; 2.1 Problems with terminology; 2.2 Conditions and warranties; 2.3 Termination; 2.4 Time for performance; 2.5 Time of the essence; 2.6 Notice making time of the essence; 2.7 Time at large; 2.8 Reasonable time; 2.9 Fixing time by reference to correspondence; 2.10 The effect of time at large on the contract price; Chapter 3: Damages for late completion; 3.1 Liquidated and general damages distinguished
3.2 Principles of general damages3.3 Alternative remedies; 3.4 Can general damages exceed liquidated damages?; 3.5 Under-liquidation of damages; 3.6 Double damages; 3.7 Liability for damages in tort; 3.8 The Panatown problem; Chapter 4: Liquidated damages and penalties; 4.1 Penalties-general introduction; 4.2 Liquidated damages; 4.3 Liquidated damages and penalties distinguished; 4.4 Pre-estimates of damage; 4.5 Particular aspects of penalty clauses; 4.6 Evidential matters; 4.7 Bonus clauses; 4.8 Site occupation charges; Chapter 5: Prevention; 5.1 Principle of prevention
5.2 Need for extension of time provisions5.3 Defining an act of prevention; 5.4 Prevention after the completion date; 5.5 Effect of late variations on unliquidated damages; 5.6 Prevention and time at large; 5.7 Conditions precedent and time-bars; 5.8 Steria Ltd v. Sigma Wireless Communications Ltd (2007); Chapter 6: Legal construction of liquidated damages clauses; 6.1 Rules of construction; 6.2 Contra proferentem rule; 6.3 Restrictions on implied terms; 6.4 'Catch all' phrases; 6.5 Inconsistencies in drafting; Chapter 7: Effects of determination; 7.1 The question of continuing responsibility
7.2 British Glanzstoff7.3 Contractual provisions; 7.4 Novations; 7.5 Summary on liquidated damages; 7.6 Determination and limitation on liability; Chapter 8: Problems with sectional completion; 8.1 Discovering the parties' intentions; 8.2 Proportioning down clauses; 8.3 Provisions for sectional completion; 8.4 Requirements not fully specified; Chapter 9: Application to sub-contractors; 9.1 Effect of 'stepping-down' provisions; 9.2 Can there be a genuine pre-estimate of loss?; 9.3 Commercial considerations; 9.4 Nominated sub-contracts; Chapter 10: Recovery of liquidated damages
10.1 When do liquidated damages become payable?10.2 Meaning of completion; 10.3 Certificates and conditions precedent; 10.4 Methods of recovery; 10.5 Time limits on recovery; 10.6 Interest on repayment; 10.7 Withholding notices; 10.8 Decisions of adjudicators; Chapter 11: Defences / challenges to liquidated damages; 11.1 Benefits of precedents; 11.2 Extension of time due; 11.3 Completion achieved earlier than certified; 11.4 Certificates not valid; 11.5 Conditions precedent not observed; 11.6 No date for commencement; 11.7 Prevention; 11.8 Penalties; 11.9 Provisions void for uncertainty
11.10 Waiver / estoppel
Record Nr. UNINA-9910146121103321
Eggleston Brian, CEng  
Chichester, U.K. ; ; Ames, Iowa, : Wiley-Blackwell Pub., 2009
Materiale a stampa
Lo trovi qui: Univ. Federico II
Opac: Controlla la disponibilità qui
Liquidated damages and extensions of time in construction contracts / / Brian Eggleston
Liquidated damages and extensions of time in construction contracts / / Brian Eggleston
Autore Eggleston Brian, CEng
Edizione [3rd ed.]
Pubbl/distr/stampa Chichester, U.K. ; ; Ames, Iowa, : Wiley-Blackwell Pub., 2009
Descrizione fisica 1 online resource (406 p.)
Disciplina 343.41/078624
Soggetto topico Construction contracts - England
Performance (Law) - England
Breach of contract - England
Damages - England
Time (Law) - England
Construction contracts - Wales
Performance (Law) - Wales
Breach of contract - Wales
Damages - Wales
Time (Law) - Wales
ISBN 9786612034558
9781282034556
1282034553
9781444301625
1444301624
9781444301632
1444301632
Formato Materiale a stampa
Livello bibliografico Monografia
Lingua di pubblicazione eng
Nota di contenuto Contents; Preface to Third Edition; References; Acknowledgements; Chapter 1: Introduction; 1.1 General overview; 1.2 Legal developments; 1.3 Contractual developments; Chapter 2: Time in contracts; 2.1 Problems with terminology; 2.2 Conditions and warranties; 2.3 Termination; 2.4 Time for performance; 2.5 Time of the essence; 2.6 Notice making time of the essence; 2.7 Time at large; 2.8 Reasonable time; 2.9 Fixing time by reference to correspondence; 2.10 The effect of time at large on the contract price; Chapter 3: Damages for late completion; 3.1 Liquidated and general damages distinguished
3.2 Principles of general damages3.3 Alternative remedies; 3.4 Can general damages exceed liquidated damages?; 3.5 Under-liquidation of damages; 3.6 Double damages; 3.7 Liability for damages in tort; 3.8 The Panatown problem; Chapter 4: Liquidated damages and penalties; 4.1 Penalties-general introduction; 4.2 Liquidated damages; 4.3 Liquidated damages and penalties distinguished; 4.4 Pre-estimates of damage; 4.5 Particular aspects of penalty clauses; 4.6 Evidential matters; 4.7 Bonus clauses; 4.8 Site occupation charges; Chapter 5: Prevention; 5.1 Principle of prevention
5.2 Need for extension of time provisions5.3 Defining an act of prevention; 5.4 Prevention after the completion date; 5.5 Effect of late variations on unliquidated damages; 5.6 Prevention and time at large; 5.7 Conditions precedent and time-bars; 5.8 Steria Ltd v. Sigma Wireless Communications Ltd (2007); Chapter 6: Legal construction of liquidated damages clauses; 6.1 Rules of construction; 6.2 Contra proferentem rule; 6.3 Restrictions on implied terms; 6.4 'Catch all' phrases; 6.5 Inconsistencies in drafting; Chapter 7: Effects of determination; 7.1 The question of continuing responsibility
7.2 British Glanzstoff7.3 Contractual provisions; 7.4 Novations; 7.5 Summary on liquidated damages; 7.6 Determination and limitation on liability; Chapter 8: Problems with sectional completion; 8.1 Discovering the parties' intentions; 8.2 Proportioning down clauses; 8.3 Provisions for sectional completion; 8.4 Requirements not fully specified; Chapter 9: Application to sub-contractors; 9.1 Effect of 'stepping-down' provisions; 9.2 Can there be a genuine pre-estimate of loss?; 9.3 Commercial considerations; 9.4 Nominated sub-contracts; Chapter 10: Recovery of liquidated damages
10.1 When do liquidated damages become payable?10.2 Meaning of completion; 10.3 Certificates and conditions precedent; 10.4 Methods of recovery; 10.5 Time limits on recovery; 10.6 Interest on repayment; 10.7 Withholding notices; 10.8 Decisions of adjudicators; Chapter 11: Defences / challenges to liquidated damages; 11.1 Benefits of precedents; 11.2 Extension of time due; 11.3 Completion achieved earlier than certified; 11.4 Certificates not valid; 11.5 Conditions precedent not observed; 11.6 No date for commencement; 11.7 Prevention; 11.8 Penalties; 11.9 Provisions void for uncertainty
11.10 Waiver / estoppel
Record Nr. UNINA-9911019832203321
Eggleston Brian, CEng  
Chichester, U.K. ; ; Ames, Iowa, : Wiley-Blackwell Pub., 2009
Materiale a stampa
Lo trovi qui: Univ. Federico II
Opac: Controlla la disponibilità qui