Building contract claims [[electronic resource]]
| Building contract claims [[electronic resource]] |
| Autore | Chappell David |
| Edizione | [4th ed. /] |
| Pubbl/distr/stampa | Oxford, : Blackwell, 2005 |
| Descrizione fisica | 1 online resource (xi, 552 p. ) : ill |
| Disciplina | 343.41078624 |
| Altri autori (Persone) |
Powell-SmithVincent
SimsJohn <1929-> ChappellDavid |
| Soggetto topico |
Construction contracts - Great Britain
Breach of contract - Great Britain Actions and defenses - Great Britain Damages - Great Britain Law Construction contracts - England Breach of contract - England Actions and defenses - England Damages - England Law - Great Britain Law - Non-U.S Law, Politics & Government |
| Soggetto genere / forma | Electronic books. |
| ISBN |
1-280-21296-9
9786610212965 0-470-79917-X 0-470-75932-1 1-4051-4808-X |
| Formato | Materiale a stampa |
| Livello bibliografico | Monografia |
| Lingua di pubblicazione | eng |
| Nota di contenuto | PART 1.1 Introduction.1.1 Structure of the book.1.2 Definitions.1.3 The basis of claims.1.4 Architect's and Contract Administrator's powers and liability to the contractor.1.5 Quantity surveyor's powers.2 Time.2.1 Time of the essence.2.2 Time at large.2.3 Extension of time clauses in contracts.2.4 Concurrency.2.5 Acceleration.2.6 Sectional completion.2.7 The SCL extension of time protocol.3 Liquidated damages.3.1 The meaning and purpose of liquidated damages.3.2 Liquidated damages or penalty.3.3 Liquidated damages as limitation of liability.3.4 Sums greater than a genuine pre-estimate.3.5 Liquidated damages as an exhaustive remedy.3.6 Injunction.3.7 Liquidated damages in relation to loss.3.8 Where there is no breach of contract.3.9 Calculation of liquidated damages.3.10 Maximum recovery if sum is a penalty.3.11 Maximum recovery if liquidated damages do not apply.3.12 Bonus clauses.4 Basis for common law claims.4.1 General.4.2 Implied terms in building contracts.4.3 Variation of contract.4.4 Omission of work to give it to others.4.5 Extra work.4.6 Possession of site.4.7 Site conditions.5 Direct loss and/or expense.5.1 Introduction.5.2 Direct v indirect.6 Potential heads of claim.6.1 Basic principles.6.2 Two basic claims situations.6.3 Foreshortened programme.6.4 The 'knock-on' effect.6.5 The more common heads of loss.6.6 Cost of a claim.7 Causation.7.1 Theory.7.2 Use of networks.7.3 Float.8 The global approach.9 Substantiation of claims.9.1 Principles.9.2 Nature of supporting evidence.9.3 'Scott Schedule'.PART 2.10 Extension of time under JCT standard form contracts.10.1 Extension of time position under JCT 98.10.2 Extension of time position under IFC 98.10.3 Extension of time position under MW 98.10.4 Extension of time position under WCD 98.10.5 Extension of time position under PCC 98.10.6 Extension of time position under MC 98.10.7 Extension of time position under TC/C 02.10.8 Extension of time position under MPF 03.11 Liquidated damages under JCT standard form contracts.11.1 Liquidated damages position under JCT 98.11.2 Liquidated damages position under IFC 98.11.3 Liquidated damages position under MW 98.11.4 Liquidated damages position under WCD 98.11.5 Liquidated damages position under PCC 98.11.6 Liquidated damages position under MC 98.11.7 Liquidated damages position under TC/C 02.11.8 Liquidated damages position under MPF 03.12 Loss and/or expense under JCT standard form contracts.12.1 Introduction.12.2 Under JCT 98.12.3 Under JCT IFC 98.12.4 Under JCT MW 98.12.5 Under JCT WCD 98.12.6 Under JCT PCC 98.12.7 Under JCT MC 98.12.8 Under JCT TC/C 02.12.9 Under JCT MPF 03.13 Variations.13.1 Introduction.13.2 The baseline.13.3 Bills of quantities.13.4 Functions of the architect and the quantity surveyor.13.5 Variations position under JCT 98.13.6 Variations position under IFC 98.13.7 Variations position under MW 98.13.8 Variations position under WCD 98.13.9 Variations position under PCC 98.13.10 Variations position under MC 98.13.11 Variations position under TC/C 02.13.12 Variations position under MPF 03.PART 3.14 Claims under GC/Works/1 (1998).14.1 Introduction.14.2 Valuation of instructions.14.3 Prolongation and disruption.14.4 Extension of time and liquidated damages.15 Variations and claims under ACA 3.15.1 Introduction.15.2 Monetary claims under ACA 3.15.3 Architect's instructions.15.4 Extension of time and liquidated damages.15.5 Claims on the final certificate.16 Claims under NEC.16.1 Introduction.16.2 Compensation events.16.3 Delay damages.17 Sub-contract claims.17.1 Introduction.17.2 Nominated sub-contract form NSC/C.17.3 Domestic sub-contract form DSC.17.4 Sub-contract conditions for sub-contractors named under IFC 98 (NAM/SC).17.5 The IN/SC form of domestic sub-contract for use with IFC 98.17.6 The Works Contract/2 for use with MC 98.17.7 The ACA form of sub-contract.Appendix A: Example of build up of contractor's entitlement to reimbursement of direct loss and/or expense under JCT 98, clause 26.Appendix B: Extension of time and money claims under DOM/1.Table of cases.Table of standard form contract clauses.Index |
| Altri titoli varianti | Building Contract Claims 4e |
| Record Nr. | UNISA-996214615303316 |
Chappell David
|
||
| Oxford, : Blackwell, 2005 | ||
| Lo trovi qui: Univ. di Salerno | ||
| ||
The Case of John Coombes, Valentine Houseman, and Edward Pearce [[electronic resource]]
| The Case of John Coombes, Valentine Houseman, and Edward Pearce [[electronic resource]] |
| Pubbl/distr/stampa | [London, : s.n., 1682?] |
| Descrizione fisica | 1 sheet ([1] p.) |
| Soggetto topico |
Breach of contract - England
Debtor and creditor - England |
| Formato | Materiale a stampa |
| Livello bibliografico | Monografia |
| Lingua di pubblicazione | eng |
| Record Nr. | UNISA-996397259403316 |
| [London, : s.n., 1682?] | ||
| Lo trovi qui: Univ. di Salerno | ||
| ||
The Case of John Coombes, Valentine Houseman, and Edward Pearce [[electronic resource]]
| The Case of John Coombes, Valentine Houseman, and Edward Pearce [[electronic resource]] |
| Pubbl/distr/stampa | [S.l., : s.n., 1676] |
| Descrizione fisica | 1 sheet ([1] p.) |
| Soggetto topico |
Breach of contract - England
Extinguishment of debts - England |
| Formato | Materiale a stampa |
| Livello bibliografico | Monografia |
| Lingua di pubblicazione | eng |
| Record Nr. | UNISA-996389745503316 |
| [S.l., : s.n., 1676] | ||
| Lo trovi qui: Univ. di Salerno | ||
| ||
Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell
| Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell |
| Autore | Carnell Nicholas J |
| Edizione | [2nd ed.] |
| Pubbl/distr/stampa | Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005 |
| Descrizione fisica | 1 online resource (320 p.) |
| Disciplina | 343.41078624 |
| Soggetto topico |
Construction contracts - England
Breach of contract - England Time (Law) - England Construction industry - Management |
| Soggetto genere / forma | Electronic books. |
| ISBN |
1-281-84097-1
9786611840976 0-470-75935-6 0-470-75934-8 |
| Formato | Materiale a stampa |
| Livello bibliografico | Monografia |
| Lingua di pubblicazione | eng |
| Nota di contenuto |
Contents; Preface; Acknowledgements; List of Abbreviations; 1 Time is Money; 1.1 Introduction; 1.2 An outline of the battlefield - looking forward; 2 Planning the Project; 2.1 Allocating risk; 2.2 Timing obligations; 2.3 Planning tools; 2.4 Information - when and what; 2.5 Getting it right from the outset - contractual obligations; 2.6 The employer's perspective; 3 During the Works; 3.1 Site organisation and reporting systems; 3.2 Notices; 3.3 Monitoring delays; 3.4 Conclusions; 4 Completion Dates; 4.1 Introduction; 4.2 Defining completion; 4.3 Calculating the delay
4.4 Certificates of non-completion4.5 The duty to review; 4.6 Sectional completion; 4.7 The final certificate; 4.8 Time at large; 5 Claim Preparation: Preliminary Considerations; 5.1 Objectives; 5.2 Example in practice; 5.3 Means and ends; 5.4 The legal framework; 6 Legal Considerations; 6.1 When does a dispute become 'legal'?; 6.2 Claims as negotiating tools; 6.3 Showing cause and effect; 6.4 Legal and practical consequences; 7 Analysing the Causes of Delay: Planning and Networks; 7.1 Objectives; 7.2 Strategic planning; 7.3 Project network techniques in programme preparation 7.4 The critical path7.5 Resource analysis; 7.6 Overview; 8 Delay Analysis; 8.1 Introduction; 8.2 Tender and programme analysis; 8.3 Cause and effect; 8.4 Analysing the effect of delays; 8.5 Float; 9 The SCL Protocol; 9.1 Introduction; 9.2 Practical concerns; 9.3 Programme and records; 9.4 Principles relating to delay and compensation; 9.5 Dealing with extensions of time during the project; 9.6 Dealing with disputed extensions of time after the project; 9.7 The PFE Change Management Supplement; 9.8 Some thoughts going forward; 10 Presentation of the Claim; 10.1 General 10.2 Putting together the submission10.3 Presenting the evidence; 10.4 Witnesses of fact; 10.5 Claims consultants; 10.6 Expert evidence; 11 Dispute Resolution; 11.1 Changing times; 11.2 Adjudication; 11.3 Mediation and alternative dispute resolution; Appendix 1 Sample Preliminary Clauses Dealing with Programmes; Appendix 2 Draft Notices of Delay; Notes; Table of Cases; Table of Statutes; Bibliography; Index |
| Record Nr. | UNINA-9910144094703321 |
Carnell Nicholas J
|
||
| Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005 | ||
| Lo trovi qui: Univ. Federico II | ||
| ||
Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell
| Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell |
| Autore | Carnell Nicholas J |
| Edizione | [2nd ed.] |
| Pubbl/distr/stampa | Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005 |
| Descrizione fisica | 1 online resource (320 p.) |
| Disciplina | 343.41078624 |
| Soggetto topico |
Construction contracts - England
Breach of contract - England Time (Law) - England Construction industry - Management |
| ISBN |
1-281-84097-1
9786611840976 0-470-75935-6 0-470-75934-8 |
| Formato | Materiale a stampa |
| Livello bibliografico | Monografia |
| Lingua di pubblicazione | eng |
| Nota di contenuto |
Contents; Preface; Acknowledgements; List of Abbreviations; 1 Time is Money; 1.1 Introduction; 1.2 An outline of the battlefield - looking forward; 2 Planning the Project; 2.1 Allocating risk; 2.2 Timing obligations; 2.3 Planning tools; 2.4 Information - when and what; 2.5 Getting it right from the outset - contractual obligations; 2.6 The employer's perspective; 3 During the Works; 3.1 Site organisation and reporting systems; 3.2 Notices; 3.3 Monitoring delays; 3.4 Conclusions; 4 Completion Dates; 4.1 Introduction; 4.2 Defining completion; 4.3 Calculating the delay
4.4 Certificates of non-completion4.5 The duty to review; 4.6 Sectional completion; 4.7 The final certificate; 4.8 Time at large; 5 Claim Preparation: Preliminary Considerations; 5.1 Objectives; 5.2 Example in practice; 5.3 Means and ends; 5.4 The legal framework; 6 Legal Considerations; 6.1 When does a dispute become 'legal'?; 6.2 Claims as negotiating tools; 6.3 Showing cause and effect; 6.4 Legal and practical consequences; 7 Analysing the Causes of Delay: Planning and Networks; 7.1 Objectives; 7.2 Strategic planning; 7.3 Project network techniques in programme preparation 7.4 The critical path7.5 Resource analysis; 7.6 Overview; 8 Delay Analysis; 8.1 Introduction; 8.2 Tender and programme analysis; 8.3 Cause and effect; 8.4 Analysing the effect of delays; 8.5 Float; 9 The SCL Protocol; 9.1 Introduction; 9.2 Practical concerns; 9.3 Programme and records; 9.4 Principles relating to delay and compensation; 9.5 Dealing with extensions of time during the project; 9.6 Dealing with disputed extensions of time after the project; 9.7 The PFE Change Management Supplement; 9.8 Some thoughts going forward; 10 Presentation of the Claim; 10.1 General 10.2 Putting together the submission10.3 Presenting the evidence; 10.4 Witnesses of fact; 10.5 Claims consultants; 10.6 Expert evidence; 11 Dispute Resolution; 11.1 Changing times; 11.2 Adjudication; 11.3 Mediation and alternative dispute resolution; Appendix 1 Sample Preliminary Clauses Dealing with Programmes; Appendix 2 Draft Notices of Delay; Notes; Table of Cases; Table of Statutes; Bibliography; Index |
| Record Nr. | UNISA-996203741403316 |
Carnell Nicholas J
|
||
| Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005 | ||
| Lo trovi qui: Univ. di Salerno | ||
| ||
Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell
| Causation and delay in construction disputes [[electronic resource] /] / Nicholas J. Carnell |
| Autore | Carnell Nicholas J |
| Edizione | [2nd ed.] |
| Pubbl/distr/stampa | Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005 |
| Descrizione fisica | 1 online resource (320 p.) |
| Disciplina | 343.41078624 |
| Soggetto topico |
Construction contracts - England
Breach of contract - England Time (Law) - England Construction industry - Management |
| ISBN |
1-281-84097-1
9786611840976 0-470-75935-6 0-470-75934-8 |
| Formato | Materiale a stampa |
| Livello bibliografico | Monografia |
| Lingua di pubblicazione | eng |
| Nota di contenuto |
Contents; Preface; Acknowledgements; List of Abbreviations; 1 Time is Money; 1.1 Introduction; 1.2 An outline of the battlefield - looking forward; 2 Planning the Project; 2.1 Allocating risk; 2.2 Timing obligations; 2.3 Planning tools; 2.4 Information - when and what; 2.5 Getting it right from the outset - contractual obligations; 2.6 The employer's perspective; 3 During the Works; 3.1 Site organisation and reporting systems; 3.2 Notices; 3.3 Monitoring delays; 3.4 Conclusions; 4 Completion Dates; 4.1 Introduction; 4.2 Defining completion; 4.3 Calculating the delay
4.4 Certificates of non-completion4.5 The duty to review; 4.6 Sectional completion; 4.7 The final certificate; 4.8 Time at large; 5 Claim Preparation: Preliminary Considerations; 5.1 Objectives; 5.2 Example in practice; 5.3 Means and ends; 5.4 The legal framework; 6 Legal Considerations; 6.1 When does a dispute become 'legal'?; 6.2 Claims as negotiating tools; 6.3 Showing cause and effect; 6.4 Legal and practical consequences; 7 Analysing the Causes of Delay: Planning and Networks; 7.1 Objectives; 7.2 Strategic planning; 7.3 Project network techniques in programme preparation 7.4 The critical path7.5 Resource analysis; 7.6 Overview; 8 Delay Analysis; 8.1 Introduction; 8.2 Tender and programme analysis; 8.3 Cause and effect; 8.4 Analysing the effect of delays; 8.5 Float; 9 The SCL Protocol; 9.1 Introduction; 9.2 Practical concerns; 9.3 Programme and records; 9.4 Principles relating to delay and compensation; 9.5 Dealing with extensions of time during the project; 9.6 Dealing with disputed extensions of time after the project; 9.7 The PFE Change Management Supplement; 9.8 Some thoughts going forward; 10 Presentation of the Claim; 10.1 General 10.2 Putting together the submission10.3 Presenting the evidence; 10.4 Witnesses of fact; 10.5 Claims consultants; 10.6 Expert evidence; 11 Dispute Resolution; 11.1 Changing times; 11.2 Adjudication; 11.3 Mediation and alternative dispute resolution; Appendix 1 Sample Preliminary Clauses Dealing with Programmes; Appendix 2 Draft Notices of Delay; Notes; Table of Cases; Table of Statutes; Bibliography; Index |
| Record Nr. | UNINA-9910830484503321 |
Carnell Nicholas J
|
||
| Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005 | ||
| Lo trovi qui: Univ. Federico II | ||
| ||
Causation and delay in construction disputes / / Nicholas J. Carnell
| Causation and delay in construction disputes / / Nicholas J. Carnell |
| Autore | Carnell Nicholas J |
| Edizione | [2nd ed.] |
| Pubbl/distr/stampa | Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005 |
| Descrizione fisica | 1 online resource (320 p.) |
| Disciplina | 343.73/078624 |
| Soggetto topico |
Construction contracts - England
Breach of contract - England Time (Law) - England Construction industry - Management |
| ISBN |
9786611840976
9781281840974 1281840971 9780470759356 0470759356 9780470759349 0470759348 |
| Formato | Materiale a stampa |
| Livello bibliografico | Monografia |
| Lingua di pubblicazione | eng |
| Nota di contenuto |
Contents; Preface; Acknowledgements; List of Abbreviations; 1 Time is Money; 1.1 Introduction; 1.2 An outline of the battlefield - looking forward; 2 Planning the Project; 2.1 Allocating risk; 2.2 Timing obligations; 2.3 Planning tools; 2.4 Information - when and what; 2.5 Getting it right from the outset - contractual obligations; 2.6 The employer's perspective; 3 During the Works; 3.1 Site organisation and reporting systems; 3.2 Notices; 3.3 Monitoring delays; 3.4 Conclusions; 4 Completion Dates; 4.1 Introduction; 4.2 Defining completion; 4.3 Calculating the delay
4.4 Certificates of non-completion4.5 The duty to review; 4.6 Sectional completion; 4.7 The final certificate; 4.8 Time at large; 5 Claim Preparation: Preliminary Considerations; 5.1 Objectives; 5.2 Example in practice; 5.3 Means and ends; 5.4 The legal framework; 6 Legal Considerations; 6.1 When does a dispute become 'legal'?; 6.2 Claims as negotiating tools; 6.3 Showing cause and effect; 6.4 Legal and practical consequences; 7 Analysing the Causes of Delay: Planning and Networks; 7.1 Objectives; 7.2 Strategic planning; 7.3 Project network techniques in programme preparation 7.4 The critical path7.5 Resource analysis; 7.6 Overview; 8 Delay Analysis; 8.1 Introduction; 8.2 Tender and programme analysis; 8.3 Cause and effect; 8.4 Analysing the effect of delays; 8.5 Float; 9 The SCL Protocol; 9.1 Introduction; 9.2 Practical concerns; 9.3 Programme and records; 9.4 Principles relating to delay and compensation; 9.5 Dealing with extensions of time during the project; 9.6 Dealing with disputed extensions of time after the project; 9.7 The PFE Change Management Supplement; 9.8 Some thoughts going forward; 10 Presentation of the Claim; 10.1 General 10.2 Putting together the submission10.3 Presenting the evidence; 10.4 Witnesses of fact; 10.5 Claims consultants; 10.6 Expert evidence; 11 Dispute Resolution; 11.1 Changing times; 11.2 Adjudication; 11.3 Mediation and alternative dispute resolution; Appendix 1 Sample Preliminary Clauses Dealing with Programmes; Appendix 2 Draft Notices of Delay; Notes; Table of Cases; Table of Statutes; Bibliography; Index |
| Record Nr. | UNINA-9911019651703321 |
Carnell Nicholas J
|
||
| Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005 | ||
| Lo trovi qui: Univ. Federico II | ||
| ||
Foreign currency : claims, judgments, and damages / / Michael Howard, John Knott, John Kimbell
| Foreign currency : claims, judgments, and damages / / Michael Howard, John Knott, John Kimbell |
| Autore | Knott John (Writer on law) |
| Edizione | [First edition.] |
| Pubbl/distr/stampa | Abingdon, Oxon : , : Informa Law from Routledge, , 2016 |
| Descrizione fisica | 1 online resource (392 pages) |
| Disciplina |
343.42/032
343.42032 |
| Altri autori (Persone) |
HowardM. N (Michael Newman)
KimbellJohn A (John Ashley) |
| Collana | Lloyd's Commercial Law Library |
| Soggetto topico |
Foreign exchange - Law and legislation - England
Damages - England Breach of contract - England Torts - England |
| ISBN |
9781317659280
1317659287 9781315766058 1315766051 9781317659297 1317659295 |
| Formato | Materiale a stampa |
| Livello bibliografico | Monografia |
| Lingua di pubblicazione | eng |
| Nota di contenuto | ch. 1. Introduction -- ch. 2. Basic concepts -- ch. 3. Sterling : its historical role, and the decline that led to a change in the law -- ch. 4. The Euro zone -- ch. 5. The change in English law introduced by Miliangos and its forebears -- ch. 6. Contract -- ch. 7. Tort -- ch. 8. Restitution and unjust enrichment -- ch. 9. The law of trusts and fiduciaries -- ch. 10. Claims against limited or common funds -- ch. 11. Set-off -- ch. 12. Interest -- ch. 13. Are currency exchange losses recoverable as damages? -- ch. 14. Procedure and evidence -- ch. 15. Fiat money, legal tender and alternative money. |
| Record Nr. | UNINA-9910149440203321 |
Knott John (Writer on law)
|
||
| Abingdon, Oxon : , : Informa Law from Routledge, , 2016 | ||
| Lo trovi qui: Univ. Federico II | ||
| ||
Liquidated damages and extensions of time in construction contracts [[electronic resource] /] / Brian Eggleston
| Liquidated damages and extensions of time in construction contracts [[electronic resource] /] / Brian Eggleston |
| Autore | Eggleston Brian, CEng |
| Edizione | [3rd ed.] |
| Pubbl/distr/stampa | Chichester, U.K. ; ; Ames, Iowa, : Wiley-Blackwell Pub., 2009 |
| Descrizione fisica | 1 online resource (406 p.) |
| Disciplina |
343.41
343.41/078624 |
| Soggetto topico |
Construction contracts - England
Performance (Law) - England Breach of contract - England Damages - England Time (Law) - England Construction contracts - Wales Performance (Law) - Wales Breach of contract - Wales Damages - Wales Time (Law) - Wales |
| Soggetto genere / forma | Electronic books. |
| ISBN |
1-282-03455-3
9786612034558 1-4443-0162-4 1-4443-0163-2 |
| Formato | Materiale a stampa |
| Livello bibliografico | Monografia |
| Lingua di pubblicazione | eng |
| Nota di contenuto |
Contents; Preface to Third Edition; References; Acknowledgements; Chapter 1: Introduction; 1.1 General overview; 1.2 Legal developments; 1.3 Contractual developments; Chapter 2: Time in contracts; 2.1 Problems with terminology; 2.2 Conditions and warranties; 2.3 Termination; 2.4 Time for performance; 2.5 Time of the essence; 2.6 Notice making time of the essence; 2.7 Time at large; 2.8 Reasonable time; 2.9 Fixing time by reference to correspondence; 2.10 The effect of time at large on the contract price; Chapter 3: Damages for late completion; 3.1 Liquidated and general damages distinguished
3.2 Principles of general damages3.3 Alternative remedies; 3.4 Can general damages exceed liquidated damages?; 3.5 Under-liquidation of damages; 3.6 Double damages; 3.7 Liability for damages in tort; 3.8 The Panatown problem; Chapter 4: Liquidated damages and penalties; 4.1 Penalties-general introduction; 4.2 Liquidated damages; 4.3 Liquidated damages and penalties distinguished; 4.4 Pre-estimates of damage; 4.5 Particular aspects of penalty clauses; 4.6 Evidential matters; 4.7 Bonus clauses; 4.8 Site occupation charges; Chapter 5: Prevention; 5.1 Principle of prevention 5.2 Need for extension of time provisions5.3 Defining an act of prevention; 5.4 Prevention after the completion date; 5.5 Effect of late variations on unliquidated damages; 5.6 Prevention and time at large; 5.7 Conditions precedent and time-bars; 5.8 Steria Ltd v. Sigma Wireless Communications Ltd (2007); Chapter 6: Legal construction of liquidated damages clauses; 6.1 Rules of construction; 6.2 Contra proferentem rule; 6.3 Restrictions on implied terms; 6.4 'Catch all' phrases; 6.5 Inconsistencies in drafting; Chapter 7: Effects of determination; 7.1 The question of continuing responsibility 7.2 British Glanzstoff7.3 Contractual provisions; 7.4 Novations; 7.5 Summary on liquidated damages; 7.6 Determination and limitation on liability; Chapter 8: Problems with sectional completion; 8.1 Discovering the parties' intentions; 8.2 Proportioning down clauses; 8.3 Provisions for sectional completion; 8.4 Requirements not fully specified; Chapter 9: Application to sub-contractors; 9.1 Effect of 'stepping-down' provisions; 9.2 Can there be a genuine pre-estimate of loss?; 9.3 Commercial considerations; 9.4 Nominated sub-contracts; Chapter 10: Recovery of liquidated damages 10.1 When do liquidated damages become payable?10.2 Meaning of completion; 10.3 Certificates and conditions precedent; 10.4 Methods of recovery; 10.5 Time limits on recovery; 10.6 Interest on repayment; 10.7 Withholding notices; 10.8 Decisions of adjudicators; Chapter 11: Defences / challenges to liquidated damages; 11.1 Benefits of precedents; 11.2 Extension of time due; 11.3 Completion achieved earlier than certified; 11.4 Certificates not valid; 11.5 Conditions precedent not observed; 11.6 No date for commencement; 11.7 Prevention; 11.8 Penalties; 11.9 Provisions void for uncertainty 11.10 Waiver / estoppel |
| Record Nr. | UNINA-9910146121103321 |
Eggleston Brian, CEng
|
||
| Chichester, U.K. ; ; Ames, Iowa, : Wiley-Blackwell Pub., 2009 | ||
| Lo trovi qui: Univ. Federico II | ||
| ||
Liquidated damages and extensions of time in construction contracts / / Brian Eggleston
| Liquidated damages and extensions of time in construction contracts / / Brian Eggleston |
| Autore | Eggleston Brian, CEng |
| Edizione | [3rd ed.] |
| Pubbl/distr/stampa | Chichester, U.K. ; ; Ames, Iowa, : Wiley-Blackwell Pub., 2009 |
| Descrizione fisica | 1 online resource (406 p.) |
| Disciplina | 343.41/078624 |
| Soggetto topico |
Construction contracts - England
Performance (Law) - England Breach of contract - England Damages - England Time (Law) - England Construction contracts - Wales Performance (Law) - Wales Breach of contract - Wales Damages - Wales Time (Law) - Wales |
| ISBN |
9786612034558
9781282034556 1282034553 9781444301625 1444301624 9781444301632 1444301632 |
| Formato | Materiale a stampa |
| Livello bibliografico | Monografia |
| Lingua di pubblicazione | eng |
| Nota di contenuto |
Contents; Preface to Third Edition; References; Acknowledgements; Chapter 1: Introduction; 1.1 General overview; 1.2 Legal developments; 1.3 Contractual developments; Chapter 2: Time in contracts; 2.1 Problems with terminology; 2.2 Conditions and warranties; 2.3 Termination; 2.4 Time for performance; 2.5 Time of the essence; 2.6 Notice making time of the essence; 2.7 Time at large; 2.8 Reasonable time; 2.9 Fixing time by reference to correspondence; 2.10 The effect of time at large on the contract price; Chapter 3: Damages for late completion; 3.1 Liquidated and general damages distinguished
3.2 Principles of general damages3.3 Alternative remedies; 3.4 Can general damages exceed liquidated damages?; 3.5 Under-liquidation of damages; 3.6 Double damages; 3.7 Liability for damages in tort; 3.8 The Panatown problem; Chapter 4: Liquidated damages and penalties; 4.1 Penalties-general introduction; 4.2 Liquidated damages; 4.3 Liquidated damages and penalties distinguished; 4.4 Pre-estimates of damage; 4.5 Particular aspects of penalty clauses; 4.6 Evidential matters; 4.7 Bonus clauses; 4.8 Site occupation charges; Chapter 5: Prevention; 5.1 Principle of prevention 5.2 Need for extension of time provisions5.3 Defining an act of prevention; 5.4 Prevention after the completion date; 5.5 Effect of late variations on unliquidated damages; 5.6 Prevention and time at large; 5.7 Conditions precedent and time-bars; 5.8 Steria Ltd v. Sigma Wireless Communications Ltd (2007); Chapter 6: Legal construction of liquidated damages clauses; 6.1 Rules of construction; 6.2 Contra proferentem rule; 6.3 Restrictions on implied terms; 6.4 'Catch all' phrases; 6.5 Inconsistencies in drafting; Chapter 7: Effects of determination; 7.1 The question of continuing responsibility 7.2 British Glanzstoff7.3 Contractual provisions; 7.4 Novations; 7.5 Summary on liquidated damages; 7.6 Determination and limitation on liability; Chapter 8: Problems with sectional completion; 8.1 Discovering the parties' intentions; 8.2 Proportioning down clauses; 8.3 Provisions for sectional completion; 8.4 Requirements not fully specified; Chapter 9: Application to sub-contractors; 9.1 Effect of 'stepping-down' provisions; 9.2 Can there be a genuine pre-estimate of loss?; 9.3 Commercial considerations; 9.4 Nominated sub-contracts; Chapter 10: Recovery of liquidated damages 10.1 When do liquidated damages become payable?10.2 Meaning of completion; 10.3 Certificates and conditions precedent; 10.4 Methods of recovery; 10.5 Time limits on recovery; 10.6 Interest on repayment; 10.7 Withholding notices; 10.8 Decisions of adjudicators; Chapter 11: Defences / challenges to liquidated damages; 11.1 Benefits of precedents; 11.2 Extension of time due; 11.3 Completion achieved earlier than certified; 11.4 Certificates not valid; 11.5 Conditions precedent not observed; 11.6 No date for commencement; 11.7 Prevention; 11.8 Penalties; 11.9 Provisions void for uncertainty 11.10 Waiver / estoppel |
| Record Nr. | UNINA-9911019832203321 |
Eggleston Brian, CEng
|
||
| Chichester, U.K. ; ; Ames, Iowa, : Wiley-Blackwell Pub., 2009 | ||
| Lo trovi qui: Univ. Federico II | ||
| ||