1.

Record Nr.

UNINA9911019651703321

Autore

Carnell Nicholas J

Titolo

Causation and delay in construction disputes / / Nicholas J. Carnell

Pubbl/distr/stampa

Oxford, UK ; ; Ames, Iowa, : Blackwell Pub., c2005

ISBN

9786611840976

9781281840974

1281840971

9780470759356

0470759356

9780470759349

0470759348

Edizione

[2nd ed.]

Descrizione fisica

1 online resource (320 p.)

Disciplina

343.73/078624

Soggetti

Construction contracts - England

Breach of contract - England

Time (Law) - England

Construction industry - Management

Lingua di pubblicazione

Inglese

Formato

Materiale a stampa

Livello bibliografico

Monografia

Note generali

Description based upon print version of record.

Nota di bibliografia

Includes bibliographical references and index.

Nota di contenuto

Contents; Preface; Acknowledgements; List of Abbreviations; 1 Time is Money; 1.1 Introduction; 1.2 An outline of the battlefield - looking forward; 2 Planning the Project; 2.1 Allocating risk; 2.2 Timing obligations; 2.3 Planning tools; 2.4 Information - when and what; 2.5 Getting it right from the outset - contractual obligations; 2.6 The employer's perspective; 3 During the Works; 3.1 Site organisation and reporting systems; 3.2 Notices; 3.3 Monitoring delays; 3.4 Conclusions; 4 Completion Dates; 4.1 Introduction; 4.2 Defining completion; 4.3 Calculating the delay

4.4 Certificates of non-completion4.5 The duty to review; 4.6 Sectional completion; 4.7 The final certificate; 4.8 Time at large; 5 Claim Preparation: Preliminary Considerations; 5.1 Objectives; 5.2 Example in practice; 5.3 Means and ends; 5.4 The legal framework; 6 Legal Considerations; 6.1 When does a dispute become 'legal'?; 6.2 Claims as



negotiating tools; 6.3 Showing cause and effect; 6.4 Legal and practical consequences; 7 Analysing the Causes of Delay: Planning and Networks; 7.1 Objectives; 7.2 Strategic planning; 7.3 Project network techniques in programme preparation

7.4 The critical path7.5 Resource analysis; 7.6 Overview; 8 Delay Analysis; 8.1 Introduction; 8.2 Tender and programme analysis; 8.3 Cause and effect; 8.4 Analysing the effect of delays; 8.5 Float; 9 The SCL Protocol; 9.1 Introduction; 9.2 Practical concerns; 9.3 Programme and records; 9.4 Principles relating to delay and compensation; 9.5 Dealing with extensions of time during the project; 9.6 Dealing with disputed extensions of time after the project; 9.7 The PFE Change Management Supplement; 9.8 Some thoughts going forward; 10 Presentation of the Claim; 10.1 General

10.2 Putting together the submission10.3 Presenting the evidence; 10.4 Witnesses of fact; 10.5 Claims consultants; 10.6 Expert evidence; 11 Dispute Resolution; 11.1 Changing times; 11.2 Adjudication; 11.3 Mediation and alternative dispute resolution; Appendix 1 Sample Preliminary Clauses Dealing with Programmes; Appendix 2 Draft Notices of Delay; Notes; Table of Cases; Table of Statutes; Bibliography; Index

Sommario/riassunto

Construction claims frequently involve a dispute about delay. Whether or not the contractor or client has a claim which can be proved successfully depends on establishing causation and understanding legal rights and obligations. This book shows how to identify and avoid problems during the project, and analyses claims for delay.The new edition takes account of case law since 1999 and has new sections on adjudication, risk allocation and the Delay and Disruption Protocol.